Why is the conversion from BCY to Cy required?
The conversion from BCY to CY is required to estimate the correct quantity and costs of materials to be handled or transported after excavation. Q: How do you calculate total bank cubic yards?
How many cubic yards are in a BCY?
One Bank Cubic Yard (BCY) equals 27 cubic feet (3'x3'x3') of earth in situ. When excavated and loaded loosely into a truck, the original one BCY of material expands to approximately 1.25 Cubic Yards (CY).
What is the difference between ECY and BCY?
CY = cubic yard = usually just a “cubic yard” as calculated above ECY = embankment cubic yard = a cubic yard as it exists in an embankment made by your crew BCY = bank cubic yard = arguably identical to an ECY
What does BCY and TCY stand for?
BCY = bank cubic yard = arguably identical to an ECY TCY = truck cubic yard = cubic yard as it exists in the back of a hauling truck after placed there by your excavator Now, these acronyms vary across the country, are regional, and carry different meanings.
How is BCY calculated?
To determine the volume of dirt you will have to haul to another location on the site or off the site, you would multiply the cubic yard by a Swell Factor, which in this case would be 1.25. This would convert the 1.0 Bank Cubic Yard (BCY) to 1.25 Loose Cubic Yards (LCY).
What is BCY and CCY?
7. BCY = Bank cubic yard - one cubic yard of material as it lies in the natural state. CCY = Compacted cubic yard - one cubic yard of material after it has been compacted to specification density.
Is Cy the same as BCY?
CY = cubic yard = usually just a “cubic yard” as calculated above. ECY = embankment cubic yard = a cubic yard as it exists in an embankment made by your crew. BCY = bank cubic yard = arguably identical to an ECY.
What unit is BCY?
bank cubic yard cubic meterWith Factors for Conversion of Units to the International System of Units (SI)AbbreviationUnit of measureTo convert to-BCYbank cubic yardcubic meterd/wkday per weekNApd/yrday per yearNAp$/stdollar per short tondollar per metric ton17 more rows
What is CCY construction?
Compacted cubic yard (CCY). A CCY is 1 cubic yard of material after compaction.
What is the difference between a bank cubic yard a loose cubic yard and a compacted cubic yard Why are they important in estimating excavation?
Why are they important in estimating excavation? Bank cubic yard- represents soil in its natural condition. Cuts and excavation are measured in bank cubic yards. Loose cubic yards- represent soil after it has been excavated and has yet to be compacted.
What does Lcy mean in construction?
When preparing bids or construction cost-estimates, knowing the loose cubic yard (LCY) or bank cubic yard (BCY) quantities required for fill construction is important.
What is a loose cubic yard?
loose cubic yard (or meter) A unit to express the volume of loose material.
How many yard of dirt do I need?
Length in feet x Width in feet x Depth in feet (inches divided by 12). Take the total and divide by 27 (the amount of cubic feet in a yard). The final figure will be the estimated amount of cubic yards required.
What is bank soil and loose soil?
• Soil Conditions – Bank: Material in its natural state before. disturbance (in place) • Unit volume is Bank Cubic Meter (BCM) – Loose: Material that has been excavated or. loaded.