The best way to calculate how much concrete you will need in cubic yards is to do the following:
- Mark your area that needs concrete and divide it into smaller areas.
- Calculate the volume of your area after determining its shape (see the examples below) by multiplying it with the thickness of the concrete.
- Convert the volume from feet to cubic yards to get a precise number of concrete that you need – in cubic yards.
- Measure the area in feet.
- Multiply length by width, and then by thickness.
- Divide the resulting number by 27 to find cubic yards.
What is the formula to calculate concrete yards?
The formula for concrete calculations is (length x width x depth) divided by 27. The result of this formula provides the number of cubic yards of concrete needed. The measurements must be in feet in order for the equation to work. Concrete is comprised of several components including water, Portland cement and aggregate, which is granular ...
How do you figure out a yard of concrete?
Aside from style alone, few people know how to choose between stone, brick, or concrete pavers for their patio ... A standard patio ranges between $800 and $4,500, though the size of your yard and patio might dictate the materials you choose to work ...
How to figure how many yards of concrete you need?
To help you calculate concrete, here are a couple of steps that you can follow:
- Establish the right thickness that you want the concrete to have.
- Get the right length and width of the area that you want to cover.
- Multiply the length by width so that you can get the correct square footage.
- Convert the thickness of the concrete from inches to feet.
How do you figure a yard of concrete?
How do you figure yards of concrete? Multiply the width times the length times the height (W x L x H). You can also use our volume calculator to find cubic yardage of a space.
What is the formula for figuring concrete?
Use the formula. Calculating the volume for concrete requires using three dimensions: length times width (which is area) times the height (thickness) or L x W x H. If you are using feet as your standard unit of measurement, this formula will give you the volume of concrete in cubic feet.
How many yards of concrete do I need for a 24x24 x4 slab?
7.11 yardsFor example, for a concrete slab that is 24' X 24' X 4”, simply enter 4 in the Thickness/Depth field, 24 in the Width field, and 24 in the Length field. Click “Calculate”. Your answer should be 7.11 yards. Note: The Concrete Volume Calculator can also be used to determine yardage for aggregate products.
How many yards of concrete do I need for a 10x10 slab?
1.3 cubic yardsThe amount you will need for a 10 x 10 slab is 1.3 cubic yards, we always add an extra 10% to allow for any slab depth variations or spills that may occur.
How many sq ft does a yd of concrete cover?
Concrete volume is measured in cubic yards. When poured on a perfectly level surface, one cubic yard will cover 27 square feet at one foot thick.
How much does it cost to pour a 24x24 slab of concrete?
A typical 24x24 garage slab costs between $3,057 and $5,944 with prices ranging from $5.31 to $8.31 per square foot for a 4” reinforced slab of concrete, and $6.83 to $10.32 per square foot for a 6” slab of reinforced concrete.
How do you calculate concrete for a slab?
CONCRETE CALCULATOR FORMULADetermine how thick you want the concrete.Measure the length and width that you'd like to cover.Multiply the length by the width to determine square footage.Convert the thickness from inches to feet.Multiply the thickness in feet by the square footage to determine cubic feet.More items...•
Does a 10x10 concrete slab need rebar?
Rebar is not necessary for every concrete project. The general rule of thumb is that if you are pouring concrete that is more than 5 inches in depth, you are probably going to want to add in some rebar to help reinforce the entire structure.
How many 80lb bags of concrete do I need for a 10x10 slab?
At 4″ thick, for a 10×10 slab, generally, you will need 1.23 cubic yards or 33 cubic feet or either 74- 60lb or 56-80lb bags of premixed concrete.
How much concrete do I need for a 12x12 slab?
Regarding this, “how much concrete do I need for a 12×12 slab?”, at 4 inches thick, generally you will need approximately 1.76 cubic yards or 47.52 cubic feet or 1.35 m3 (either 104 bags of 60lb or 80 bags of 80lb) of premixed concrete for a 12×12 slab, at 5 inches thick slab, 2.22 cubic yards or 59.90 cubic feet or ...
How many yards of concrete do I need for a 10x12 slab?
Regarding this, “how much concrete do I need for a 10×12 slab?”, at 4 inches thick, generally you will need approximately 1.46 cubic yards or 39.6 cubic feet (either 86 bags of 60lb or 67 bags of 80lb) of premixed concrete for a 10×12 slab, at 5 inches thick slab, 1.85 cubic yards or 50 cubic feet (either 109 bags of ...
How many square feet will 1 yard of concrete cover at 4 inches thick?
81 square feetOne Cubic Yard of Concrete: 4-inches thick – covers 81 square feet.
How many yards of concrete do I need for 800 square feet?
As per thumb rule and guidelines, for 800 sq. ft. or (20×40) slab at 4 inch thickness, you will need approximately 10 cubic yards of concrete and at 5 inch thickness 12.5 yards of concrete you would required. Maths calculation:- 1) at 4 inch thickness, concrete quantity = 800÷80= approx 10 cu. yd.
Concrete calculator formula for floors and slabs
This is how you use a formula to calculate concrete for a square concrete slab or a rectangular shaped floor or slab.
concrete calculator formula for a round slab
The formula to calculate concrete yardage for a round slab is very different than the formula for a square slab. Square footage is calculated using Pi and the diameter of the circle to help determine cubic yardage.
calculator formula for a concrete wall
Calculating concrete yardage for a wall uses the same formula as a slab.
Formula to calculate concrete for a footer
Calculating concrete yardage for a footing is done much like a slab, you just usually have smaller units of measurement for width.
Concrete calculator formula for a square column
Calculating concrete for a square column first starts with calculating the cubic feet of the column.
Formula to calculate concrete for a round column
The formula to calculate concrete yardage for a round column is just like the round slab formula above. The difference is a column's height is usually much greater than a slab.
How to calculate concrete for steps
This is how you calculate concrete yardage for a set of concrete steps.
Should I order concrete by the yard from a ready mix company or just use bags?
Larger jobs such as driveways are easier to complete when ordering concrete by the yard, rather than trying to mix bag after bag by hand. For smaller jobs, like a walkway, modest patio or footings, you should calculate the number of concrete bags instead.
Calculating the amount of concrete needed for slabs (including odd shapes)
Rule of thumb: add 1 / 4 " to the thickness of your slab for your slab concrete budget. This assumes you have the job evenly graded to the right depth, and the grade is well compacted.
Calculating the amount of concrete needed for footings
Footings will rarely follow the drawing exactly. In rocky soil the footings may collapse when big rocks are excavated
Estimating concrete steps
Steps seem tricky to calculate but are not. If there are three steps leading up to a porch:
Calculating the amount of base fill
Granite Construction has an excellent base fill calculator on their site. Use this to figure how much material you need for the subgrade.
Requesting your ready mix supplier to visit your site
After you have chosen a Ready Mix Supplier, have a representative come to your site to give his/her opinion on the quantity required. Compare the figure with what you came up with. Discuss any variances with the supplier.
Calculator Use
Calculate volumes for concrete slabs, walls, footers, columns, steps, curbs and gutters. Enter dimensions in US units (inches or feet) or metric units (centimeters or meters) of your concrete structure to get the cubic yards value of the amount of concrete you will need to make this structure.
Curbs & Gutters
We calculate the volume in sections from the ground to the top of each section. The Curb and Gutter are each a section.
Concrete Yardage Calculator
Here is a great concrete yardage calculator for estimating how much concrete to order to complete your job. Just remember to add some extra, maybe a half yard extra, because running short is not an option.
Concrete Calculator
If you make a mistake and don't order enough concrete, just call the concrete dispatcher and he will send another concrete truck with the balance on it.
How much does concrete cost per yard?
How much is concrete a yard? The cost of concrete per cubic yard depends on which brand you purchase, but usually costs about $110 for bags .
How to calculate how much concrete I need for a slab?
How do I calculate how much concrete I need for a slab? To calculate the amount of concrete you need for a slab, you should find the cubic yardage of the area you will be filling. Just follow these steps: Measure the area in feet. Multiply length by width, and then by thickness.
How many square feet does an 80 lb bag of concrete cover?
One 80lb -bag covers an area of about 2 square feet, for a slab 4 inches thick. Two 60lb -bags of concrete cover an area of about 2 square feet for a slab that is 6 inches thick.
What factors affect the cost of concrete?
There are several things that can affect the cost of your concrete project, including: How complicated the project is: stairs will likely cost more than a slab, for example. Materials: polymer concrete is often more expensive. Labor prices: jobs that take longer and need more workers will have a higher price.
How long does it take for concrete to harden?
Here are a few common varieties of concrete: Quick-set: Hardens in 20 to 40 minutes. Best for small projects. Regular-set: 24 to 48 hour set time. Used more for large projects. High-strength: Usually sets in 10 to 12 hours.
Does adding rebar to concrete cost more?
Extra strength: adding rebar or mesh to the concrete will up the cost. Additional tasks: if pros need to remove debris, get rid of your existing patio or dig before starting, it will be more expensive.
Can you order concrete by cubic yard?
If you have a larger job, like a building a driveway or pool deck, it’s probably best to order concrete by the cubic yard or hire a concrete delivery service. For smaller jobs, like setting posts for fences or small curbs, mixing bags of concrete should be sufficient.
How do you figure square yards?
To calculate square yards (SQYDS), multiply the length times the width, in feet and divide by 9. There are 9 square feet in a square yard.
How many cubic yards do I need?
How to calculate cubic yards? The formula: Number of Cubic Yards = Length (in feet) Width (in feet) Depth (in feet) ÷ 27. Simply multiply the three dimensions together to find the number of cubic feet, then divide by 27 to find the number of cubic yards.
How much does 2 yards of concrete cost?
According to the NRMCA – Ready Mixed Concrete Industry Data Survey, the average cost of concrete in 2018 was $120 per cubic yard, or $240 for the 2 cubic yards needed for a typical 10-by-10-foot patio. Bulk Concrete Prices.
How many bags of cement do I need for 100 square feet?
4 bags ( 401 kg) of cement and 1593 nos bricks are required for 100 square feet 13.5 inch brick wall.
How many square feet does 10 yards of concrete cover?
One Cubic Yard of Concrete: 4-inches thick – covers 81 square feet. 5-inches thick – covers 65 square feet. 6-inches thick – covers 54 square feet.
How many cubic feet are in a 50 pound bag of concrete?
One 50-pound bag of Quikrete Fast Setting Concrete Mix yields about. 375 cubic feet.
How many yards are in a square yard?
How many yards in 1 square yard? The answer is 1. We assume you are converting between yard and square yard. You can view more details on each measurement unit: yards or square yard The SI derived unit for area is the square meter.
What is concrete mixed into?
Alternatively, in some factory settings, concrete is mixed into dryer forms to manufacture precast concrete products such as concrete walls. The process of concrete hardening once it has been placed is called curing, and is a slow process.
Why is concrete mixing important?
Proper mixing is essential for the production of strong , uniform concrete. It involves mixing water, aggregate, cement, and any desired additives. Production of concrete is time-sensitive, and the concrete must be placed before it hardens since it is usually prepared as a viscous fluid.
What is cement used for?
Cement is a substance that is used to bind materials, such as aggregate, by adhering to said materials, then hardening over time . While there are many types of cement, Portland cement is the most commonly used cement, and is an ingredient in concrete, mortar, and plasters.
Is concrete time sensitive?
Production of concrete is time-sensitive, and the concrete must be placed before it hardens since it is usually prepared as a viscous fluid. Some concretes are even designed to harden more quickly for applications that require rapid set time.